This Order approves the Programme to construct small hydropower plants between 2009 and 2020. The Programme intends to install 190 small hydropower plants with total capacity of 100MW.



The following government bodies own the means and possibilities to use the government budget to implement measures related to this Programme:

- Ministry of Economic Development and Trade

- Department of Energy and the Industry

- State Committee on Investment and Management of State-owned Property

- Barka Tochik's Open Joint-Stock Holding Company.

 Topics mentioned most in this policy

See how often Topics get mentioned in this policy and view specific passages of text highlighted in each document.

Group
Topics
Renewable energy
Economic sector
Finance

Note

Grantham Research Institute