These Guidelines are the Guidelines for Tariff-Based Competitive Bidding Process for Procurement of Power from Grid Connected RE Power Projects for utilisation under the scheme for flexibility in Generation and Scheduling of Thermal/ Hydro Power Stations through bundling with Renewable Energy and Storage Power. The objective of this mechanism is to promote bundling of cheaper Renewable Energy (RE) with costlier Thermal Power and to promote the Renewable Purchase Obligation (RPO) of Distribution Licensees.
The Guidelines outline the bidding process and standard provisions to be included in the Power Purchase Agreement (PPA). The PPA period should not be less than 25 years from the scheduled commissioning date, as the period influences the amount of tariff to be charged. Bids are to be submitted within 22 days, and the PPA is to be signed within 170 days of the release of the bid. The Central Electricity Regulatory Commission (CERC) presides over arbitration of any tariff-related disputes.